Pilot acceptance and multi-site monitoring handover

4 days ago
2 min read

A pilot should prove that a reading can be traced from a named field device to the correct operator screen. Use one representative site to agree what constitutes a pass before repeating the installation across a fleet.

Choose a representative pilot

Select a site that shares its device, gateway and communications method with the proposed rollout. Identify the site owner, installation contact and person authorised to accept the work. Record any exceptions that need another pilot, such as a different meter family or a site with intermittent coverage.

Witness a field reading

Capture the instrument tag, local value, unit and timestamp. Compare it with the value and timestamp on the intended dashboard. Agree a tolerance that suits the instrument and the sample interval. Record the result against that site and device, including any scaling or time-zone correction.

Check loss and recovery

Use an agreed test input to show how a stale reading appears, which operator sees the exception and how recovery is recorded. Verify access with the intended operator role. Record the expected result, observed result, evidence and responsible reviewer.

Prepare the handover record

Provide a device register, signal list, dashboard index, alarm contacts and a list of agreed exceptions. Assign ownership of calibration, connectivity, software administration and first-line support. Keep credentials in the organisation’s approved access system.

Release the remaining sites

Agree which pilot settings can be reused and which values must change for every site. Start each site with its own tags, delivery details and acceptance record. Track exceptions, open actions, sign-off date and the person responsible for closing each action.